Prerequisite Tree (PRT)

An obstacle-focused planning tool that converts hurdles into positive intermediate milestones for implementation.

🎯 What Problem It Solves

Teams are often overwhelmed by barriers (e.g., no budget, raw tech) when starting a project. The PRT converts negative obstacles into positive milestones.


🧠 Thinking Logic & Core Concepts

To achieve a goal, any obstacle must be overcome. An Intermediate Objective (IO) is defined to overcome each obstacle. Placing these in logical order forms the perfect execution map.


πŸ“‹ Newbie Step-by-Step Guide

  1. Set Target: Place the ultimate goal at the top.
  2. List Obstacles: List every barrier in the middle.
  3. Define IOs: For each obstacle, write down the positive state when it is overcome.
  4. Sequence IOs: Connect them with arrows indicating prerequisite order.
  5. Plan Execution: Translate the ordered IOs into a project schedule.

πŸ’‘ Classic Example

[In-house Core System Case]

  • Goal: High-performance core system owned entirely in-house.
  • Obstacle: Team lacks framework expertise.
  • IO: Complete a 2-week immersive bootcamp with a senior advisor.
  • Obstacle: Production servers don't support high concurrency.
  • IO: Provision elastic cloud instances by Week 3.